COMMERCE · QUOTATION PRACTICE
Every boundary you leave open in the contract ends up quietly deducted from your margin.
01
Pre-Sales Tech: Lock the Technical Boundaries First
Drawings, codes and load standards must be fixed
State clearly the applicable code (GB / EN1090 / AISC / local code), and the wind, snow, seismic and corrosion-protection grades, plus whether a third-party calculation report is required. Once the standard is vague, later upgrades to material, inspection and paint become very passive.
WARNING
"Fabricate per the foreign drawings" without verifying the code — if material, inspection or paint standards do not match, both the price increase and the schedule claim become extremely hard to negotiate.
Itemize the scope to avoid omissions
The most common way export quotes lose margin is omitted scope. Confirm item by item whether each of the following is included:
■ Detail drawings, BIM modeling, shop pre-assembly
■ NDT UT / MT / RT, weld test plates, WPS / PQR procedure qualification
■ Third-party inspection (SGS / CCIC), English documents, English MTC
Also define the component boundary: are bolt balls, sleeves, high-strength bolts, studs, bearings, purlins, cladding and fireproofing included? Many tenders only say "steel structure" with a very blurry boundary — it must be written into the quote scope.
Material requirements
State the grade, mill and MTC requirements, and whether material traceability, EU CE certification and an English material certificate are needed. Substitution rights must be written into the quote remarks — no replacement without our consent.
Coating system (a frequent export dispute)
Blast grade Sa2.5 / St3, paint brand, dry film thickness, number of primer / intermediate / top coats, and whether it resists marine atmosphere or chemical corrosion must all be specified. Overseas projects often require a salt-spray test, which is costly — if not included, it must be listed separately.
02
Production Cost Control
Weight basis: quoted weight = theoretical weight
Set the basis first so both sides do not calculate differently. Quote on theoretical weight and state the loss percentage in the remarks.
Differentiate fabrication costs
Straight members, curved parts, CHS truss, bolt-ball space frames, thick plates and high-UT requirements differ greatly in unit price. Do not apply one fabrication rate, or you either lose the bid or lose money.
Labor, NDT, welding consumables, auxiliaries, paint — review separately
Overseas projects often require a higher NDT ratio (e.g. 100% UT), which pushes inspection cost up sharply and must be a separate line item.
Pre-assembly: overseas often requires shop pre-assembly
For large space frames and trusses, the jigs, yard and crane cost of pre-assembly is easily omitted. Assess whether pre-assembly is required before quoting, then include the cost.
03
Packing, Containerization, Inland Transport
This is the part most likely to overrun the budget — always get a forwarder plan before quoting.
Packing
Rust-proof packing, VCI film, desiccant, wood skid / steel skid all count. Whether wooden packing needs fumigation / IPPC marking (mandatory in the EU, Central Asia and Southeast Asia) — if skipped, cargo is returned or fined at destination.
Two cargo types, very different freight
Normal pieces go by container; over-length / over-width / over-height pieces need flat-rack or open-top containers, with freight and reinforcement far above a normal box. Get the forwarder's plan before quoting.
Container plan and domestic inland
Estimate container count early; reinforcement, lifting lugs and bilingual marks (with project number) for oversize pieces all count. Domestic inland — factory→port freight, short lifting, port storage, port miscellaneous, manifest fee, THC — must all be included in a CIF quote.
04
Trade Terms: FOB / CIF Key Differences
You have used CIF a lot. Key reminder: under CIF the risk still transfers to the buyer after shipment. Many clients mistakenly think CIF covers destination damage, customs clearance and unloading — state it clearly in the quote remarks.
| Item |
FOB |
CIF |
| Our responsibility |
Customs clearance + pre-onboard costs |
Cost + freight + insurance (pre-onboard) |
| Risk transfer point |
After shipment → buyer |
After shipment → buyer (unchanged) |
| Freight / insurance |
Buyer bears |
We bear, included in quote |
| Destination clearance / duty / unloading |
Buyer bears |
Buyer bears (CIF does NOT cover!) |
| Sea damage / demurrage |
Buyer bears |
Buyer bears (insurance separate) |
Insurance and freight fluctuation
Under CIF, all-risks cover is default; insured value is usually 110% of cargo value, premium included in the quote, with clear start/end of cover.
TIP · FREIGHT RISK
Ocean freight fluctuates wildly. Two safe approaches: ① list freight separately with a short validity; ② lock the vessel and note "price adjustable if freight fluctuates beyond ±X%".
Demurrage and detention must be stated in the remarks: those caused by the buyer are borne by the buyer.
05
Customs, Rebate, Documents, Duty
Steel members commonly use HS code 7308; confirm early whether an export license is required.
Certificates of origin help the buyer reduce import duty — a value-add at low cost: FORM E, FORM A, and the general CO, provided as needed.
On the rebate, confirm the rebate point; the quote may reasonably pass on part of it. But document closure must hold — customs declaration, input invoice, forex receipt and contract all consistent.
Import duty and VAT are generally not our responsibility; state clearly in the quote: all destination-port taxes are borne by the buyer.
06
FX, Payment, Financing Cost
This is the top priority. Prefer RMB quotation; for foreign currency reserve a FX buffer (typically 2% ~ 4%), state a validity (mostly 3 ~ 7 days) and an adjustment mechanism in the quote, and lock FX with the bank for large forward orders.
Payment terms (export risk control)
■ New client: 30% advance, balance against B/L copy
■ Existing client / domestic EPC overseas project: progress payment negotiable
■ Large project: L/C letter of credit — review the credit early, watch for soft clauses
■ Recommended: Sinosure export credit insurance, premium in the quote, to hedge against default and country risk
When the advance is low and lead time long, calculate the cost of capital occupation and include it.
07
Quote Commercial Remarks (copy directly)
These clauses are suggested in the quote to avoid later disputes:
■ Quotation valid for XX days
■ Weight on theoretical basis, loss XX%
■ Codes, coating, NDT and inspection scope per this quote's technical attachment
■ Trade-term definition and risk division point
■ Excludes destination clearance, duty, unloading and inland transport
■ Excludes on-site erection and commissioning
■ Storage and demurrage from buyer's late take-over borne by buyer
■ Acceptance: shop pre-assembly / factory acceptance; upon arrival only quantity and appearance; sea damage by insurance
■ Warranty: 12 months from factory / arrival, whichever first; material and fabrication defects only, excluding corrosion, improper erection and service wear
CLOSING
Write the boundaries into the quote and clarify the risks — then the quotation holds up.
END