TECHNICAL · PROCESS SPECIFICATION
This specification covers welding work on bolted-sphere and welded-sphere space grid structures under conditions such as piece-by-piece erection at height, supplementary welding after integral lifting, and assembly on a working floor. It sets out the process principles, welding sequence, in-process control, post-weld inspection and safety requirements needed to control weld shrinkage, distortion and stress concentration, and to safeguard welding accuracy and structural safety.
01
General Principles and Process Philosophy
Welding at height on a space grid must follow the overall principle of "position first, then symmetry; upper chord first, then web members, and lower chord last", with control of weld shrinkage, distortion and stress concentration as the central objective. The basic process requirements are as follows:
■ Piece-by-piece erection or supplementary welding: the sequence is upper chord members → diagonal web members → lower chord members;
■ Symmetrical welding at joints: welded sphere-to-steel-tube joints are always welded symmetrically, to control member axis deviation and reduce welding stress and distortion;
■ Direction of progression: work generally spreads from the centre of the component outwards, welding the joints with the greater shrinkage first and those with less shrinkage afterwards;
■ Intersecting welds and thick plate: for intersecting welds, complete the longitudinal weld first and the transverse weld only after it has cooled to ambient temperature; thick plate should be welded in layers and in segments.
02
Pre-Construction Preparation
2.1 Technical Preparation
■ Confirm that the space grid is in position and its geometry has been corrected, and prepare the welding sequence, distortion control and lifting / supplementary erection method statements for approval before work starts;
■ Based on the joint type and member layout, draw up the welding sequence diagram, the segmented (skip) welding sequence diagram and joint details, specifying the direction and order of every weld.
2.2 Equipment and Materials
■ Check the CO2 gas-shielded welding machines, DC tack-welding machines, torches, flow meters and gas-line tightness, and confirm that gas flow, pre-flow and post-flow times meet the process requirements;
■ Bake and store welding consumables in accordance with the applicable standard; low-hydrogen electrodes should be taken out only as needed, with issue and return records kept;
■ Groove form, dimensions and cleaning quality must satisfy the design requirements; oil, rust and moisture on the groove and within the specified zone on both sides must be removed.
2.3 Working Conditions
■ Work at height may begin only after the access platforms, scaffolding, electrical safety provisions and fall-protection measures have been inspected and accepted.
03
Tack Welding
■ Tack welds are made before production welding; their length, throat and spacing are determined by calculation and kept away from member ends, corners and other stress-concentration zones;
■ Tack-welding current may be raised by about 10% to 15% over production welding to ensure good fusion of the tack welds;
■ After tack welding, check joint position, root gap and misalignment one by one; any out-of-tolerance item must be corrected before production welding begins;
■ Never place tack welds or strike an arc casually near a weld or at a critical load-bearing part of a member.
04
Welding Sequence at Height
4.1 Supplementary Welding After Integral Lifting
Weld the upper chord members first, then the diagonal web members, and the lower chord members last. This sequence improves the welding accuracy of the space grid and helps keep the crew safe.
4.2 Whole-Structure Welding After Floor Assembly
The usual order is lower chord → upper chord → web members, progressing symmetrically from the middle towards both sides.
4.3 Welded Sphere-to-Steel-Tube Joints
Use symmetrical welding, working in a pattern matched to the arrangement of members connected to the joint, so as to control member axis deviation and reduce welding stress and distortion.
4.4 General Sequencing Rules
■ Spread outwards from the centre of the component;
■ Weld the joints with greater shrinkage first, then those with less shrinkage;
■ For intersecting welds, complete the longitudinal weld first and the transverse weld after cooling to ambient temperature;
■ Thick plate should be welded in layers and in segments (skip welding).
05
Control During Welding
■ Control CO2 gas flow, shielding-gas coverage and weld-bead cleanliness to avoid porosity, lack of fusion, slag inclusions and similar defects;
■ Pre-control weld shrinkage and the distortion of integral (block) lifting; where necessary, apply preset reverse deformation, temporary supports or segmented skip welding;
■ Bake and hold electrodes and welding wire at the required quality standard before use;
■ Apply sensible preheating to slow the cooling rate in the heat-affected zone and prevent delayed cracking; the preheated zone is generally at least 1.5 times the member thickness and not less than 100 mm wide;
■ Interpass temperature, welding current, voltage and travel speed must follow the parameters of the welding procedure specification (WPS) and be recorded.
5.1 Key Welding Parameters (Reference)
| Item |
Control Requirement |
| Shielding gas |
CO2, flow set to suit the torch and working conditions Gas-line tightness, pre-flow / post-flow |
| Consumables |
Low-hydrogen electrodes taken as needed; wire baked by batch Issue and return records retained |
| Preheated zone |
At least 1.5 times the member thickness and not less than 100 mm Set by plate thickness and procedure qualification |
| Tack-welding current |
About 10% to 15% above production welding Keep away from stress-concentration zones |
| Interpass temperature |
Controlled to the WPS Thick plate welded in layers |
06
Post-Weld Treatment and Quality Inspection
■ Remove slag, spatter and surface defects promptly after welding; for welds requiring hydrogen removal, apply post-heating and heat retention in good time according to plate thickness and process requirements;
■ Once self-inspection is passed, nondestructive testing for internal defects (such as ultrasonic testing) is normally carried out within 24 hours by appropriately qualified personnel;
■ Weld quality grades are assessed against the design documents and the current standard for acceptance of construction quality of steel structures;
■ Remove burrs, slag and rust before coating; the surface rust-removal grade must meet the design or specification requirements.
6.1 Inspection Items and Requirements (Reference)
| Inspection Item |
Timing / Method and Acceptance |
| Visual inspection |
Immediately after welding, visual inspection + gauges No cracks, lack of fusion, slag inclusions, porosity or other defects above the limit |
| Internal defect testing |
Within 24 h of passing self-inspection, ultrasonic testing Assessed to the design weld quality grade and acceptance standard |
| Post-heating / dehydrogenation |
To plate thickness and process requirements Holding time and temperature to the procedure qualification |
| Surface preparation |
Before coating Rust-removal grade to the design or specification requirements |
07
Safety Essentials
■ Provide reliable working platforms, edge protection and fall arresters for welding at height, and assign a dedicated fire watch for hot work;
■ Secure cylinders, regulators and hoses against tipping; the separation between acetylene and oxygen cylinders and the distance from open flames must comply with safety rules;
■ Never place tack welds or strike an arc casually near a weld or at a critical load-bearing part of a member;
■ In high winds, rain, snow or humid conditions that impair shielding-gas effectiveness or weld quality, stop welding or take effective protective measures;
■ Keep fire extinguishers in the welding area and confirm that no ignition source remains before leaving the site.
08
Supplementary Provisions
For formal implementation, the principles in this specification should be developed into the following set of technical documents and filed together as attachments:
■ Joint details and member numbering drawings;
■ Welding parameter sheets (WPS/PQR);
■ Groove form, dimensions and cleaning requirements;
■ Segmented / skip welding sequence diagrams and distortion control measures;
■ NDT coverage, locations and acceptance criteria;
■ Safety checklist for work at height.